Battle Mountain Solar Farm EPC / Design-Build

Battle Mountain Solar Farm

Client Consolidated Edison, Inc.
Completion Date June 2021
Location Battle Mountain, Nevada
Completed by MYR Energy Services, Inc.

MYR Energy Services (MYRE) was the prime contractor for the engineer-procure-construct (EPC) delivery of this 132-MWdc photovoltaic (PV) plant, which features 100MWh/25MWdc of battery energy storage for a four-hour period. The facility’s 25 megawatts of battery capacity make it among the nation’s largest DC-coupled combined solar and battery storage system. Part of NV Energy’s Integrated Resource Plan, Battle Mountain will bring 1,001 MW of new renewable energy projects to Nevada.

Per the scope, MYRE procured the trackers, inverters, battery energy storage system (BESS), and balance of system (BOS); installed the piling, tracker, AC/DC cable, wire, and module; and conducted commissioning and testing.

RELATED NEWS: MYR Energy Services Brings DC-Coupled Solar + Storage to Battle Mountain Nevada